Kuwait City: Work on the new passenger terminal at Kuwait International Airport is on track. The T2 terminal project has so far reached 21.3 per cent, said Minister of Public Works Jenan Bushehri.
“A total of KD224.3 million have been spent on the project until July 2019, which represents 19.75 per cent of the overall cost,” she said.
Work on the new terminal started on August 28, 2016, in a project costing KD1.32 billion, Al Qabas reported.